AtkinsRéalis was commissioned by Portsmouth International Port (PIP) to assist in designing and delivering a shore power solution on 3 of its busiest berths.
Client challenge
PIP is ambitiously targeting to be Net Zero by 2030 and the UK’s first zero emission port by 2050. As such, they needed to implement a solution to drastically reduce their port emissions and improve air quality.
The busy municipal port serves cross channel ferries, cruise and freight ships across its 5 berths – with over 1.6 million passengers passing through the port in 2023 – so PIP required a solution that would not affect its operational activities. This included an electrical design that could accommodate various vessel types, whilst keeping the berths free from equipment clutter..
The port also has challenging timescales. The Zero Emission Vessels and Infrastructure (ZEVI) funding received by PIP requires the port to implement shore power and start collecting data by April 2025, and there are challenging lead times for the delivery of the specialist electrical equipment.
Our approach
AtkinsRéalis have been a key partner throughout almost every stage of the project:
- Defined project scope
- Guided the client through potential delivery models
- Provided procurement support and optioneering for specialist equipment and suppliers
- Provided commercial contract and tender management
- Led on civil and structural design and design coordination
- Managed collaboration between the port, construction contractor and supply chain
- Facilitated a coordinated construction programme through phased release of design information
- Advised on planning permissions, environmental assessments, and marine and harbour orders
- Provided electrical engineering oversight for technical reviews
- Mapped buried services and quay walls
We also produced detailed 3D models early in the design process to include multiple suppliers’ products, which helped the port to visualise the scheme and how new equipment would interact with existing fixtures and vehicles on the berths to minimise operational impact. The 3D models also enabled better engagement with key stakeholders from across the project and the same models can be used to aid future operational and maintenance phases.
Outcomes delivered
- Integrated programme being delivered on time, to budget and with minimal disruption to PIP and its operations
- Minimising risk for the client
- Reduced procurement timescales and costs for specialist equipment
- Built strong relationships with suppliers
- 3D models have informed commercial decisions and identified and resolved issues early, with fewer cost impacts
- No planned services have been cancelled or delayed as a result of survey and construction works at the port
Please note that you are now leaving the AtkinsRéalis website (legal name: AtkinsRéalis Group inc.) and entering a website maintained by a third party (the "External Website") and that you do so at your own risk.
AtkinsRéalis has no control over the External Website, any data or other content contained therein or any additional linked websites. The link to the External Website is provided for convenience purposes only. By clicking "Accept" you acknowledge and agree that AtkinsRéalis is not responsible, and does not accept or assume any responsibility or liability whatsoever for the data protection policy, the content, the data or the technical operation of the External Website and/or any linked websites and that AtkinsRéalis is not liable for the terms and conditions (or terms of use) of the External Website. Further, you acknowledge and agree that you assume all risks resulting from entering and/or using the External Website and/or any linked websites.
BY ENTERING THE EXTERNAL WEBSITE, YOU ALSO ACKNOWLEDGE AND AGREE THAT YOU COMPLETELY AND IRREVOCABLY WAIVE ANY AND ALL RIGHTS AND CLAIMS AGAINST ATKINSRÉALIS, AND RELEASE, DISCHARGE, INDEMNIFY AND HOLD HARMLESS ATKINSRÉALIS, ITS OFFICERS, EMPLOYEES, DIRECTORS AND AGENTS FROM ANY AND ALL LIABILITY INCLUDING BUT NOT LIMITED TO LIABILITY FOR LOSS, DAMAGES, EXPENSES AND COSTS ARISING OUT OF OR IN CONNECTION WITH ENTERING AND/OR USING THE EXTERNAL WEBSITE AND/OR ANY LINKED WEBSITES AND ANY DATA AND/OR CONTENT CONTAINED THEREIN.
Such waiver and release specifically includes, without limitation, any and all rights and claims pertaining to reliance on the data or content of the External Website, or claims pertaining to the processing of personal data, including but not limited to any rights under any applicable data protection statute. You also recognize by clicking “Accept” that the terms of this disclaimer are reasonable.
The information provided by Virtua Research cited herein is provided “as is” and “as available” without warranty of any kind. Use of any Virtua Research data is at a user’s own risk and Virtua Research disclaims any liability for use of the Virtua Research data. Although the information is obtained or compiled from reliable sources Virtua Research neither can nor does guarantee or make any representation or warranty, either express or implied, as to the accuracy, validity, sequence, timeliness, completeness or continued availability of any information or data, including third-party content, made available herein. In no event shall Virtua Research be liable for any decision made or action or inaction taken in reliance on any information or data, including third-party content. Virtua Research further explicitly disclaims, to the fullest extent permitted by applicable law, any warranty of any kind, whether express or implied, including warranties of merchantability, fitness for a particular purpose and non-infringement.
The consensus estimate provided by Virtua Research is based on estimates, forecasts and predictions made by third party financial analysts, as described above. It is not prepared based on information provided by AtkinsRéalis and can only be seen as a consensus view on AtkinsRéalis' possible future results from an outside perspective. AtkinsRéalis has not provided input on these forecasts, except by referring to past publicly disclosed information. AtkinsRéalis does not accept any responsibility for the quality or accuracy of any individual or average of forecasts or estimates. This web page contains forward-looking statements based on current assumptions and forecasts made by third parties. Various known and unknown risks, uncertainties and other factors could lead to material differences between AtkinsRéalis' actual future results, financial situation, development or performance, and the estimates given here.
Through the use of precise and complex digital tools, AtkinsRéalis is supporting Portsmouth International Port to design and develop a compelling carbon neutral Shore Power solution which will seamlessly serve the needs of the UK’s busiest municipal port. In working with AtkinsRéalis we are a step closer to our ambition of net zero by 2030.
Steve Watkyns
Technical Director, Portsmouth International Port
Downloads
Trade releases